Explore the key steps for creating integrated 4D/5D simulations and analyses for the National Football Stadium using BEXEL Manager and BEXEL #CDE, completed in just two weeks from a fully #BIM based model:
Day 1:
• Revit to BEXEL Publish
• Preliminary model review
Day 2:
• Elements Slicing and Landscape Modeling
Day 3:
• Automated BIM Data Enrichment
• QTO and CBS creation
• Automated Cost Database creation and fine-tuning
Day 4:
• Definition of Zones and Sub-zones
• Utilisation of existing Construction Methodology for Stadiums
Day 5:
• Automated Detailed Schedule Generation
• Construction Schedule Evaluation
• Team Planning
Day 6:
• Meeting Project Milestones
• Automated Activity Leveling
• LOB Chart Optimization
• Construction Animation fine-tuning
Day 7:
• Automated Enrichment with additional Schedule Data
• Creation of QTO and CBS based on Schedule Data
• Publish Model, Analyses and Simulations to BEXEL CDE
Day 8:
• Publish standard Power BI dashboards
• Publish customized Power BI dashboards
Day 9:
• Video Production – creation of source video materials
Day 10:
• Video Production – video editing and fine-tuning
• Integration of Expo and NFS projects
What was created:
Week1:
•Federated model with 107,556 elements in BEXEL Manager
• Over 2,000 elements that were split into smaller segments
• 172,440 classification property values added with Data Enrichment tool
• 1,367 automatically generated cost items in BEXEL Manager Cost Editor
• 118,311 quantity calculations
• Automatically Generated schedule with 2,952 tasks and 3,935 relations in BEXEL Manager
• 4 different construction schedule versions with different what-if scenarios
Week 2:
• 980,268 schedule-related property values added using BEXEL API scripts
• 15 different Custom breakdowns and Quantity Takeoffs created and published to BEXEL CDE
• 6 versions of construction schedule published on BEXEL CDE
• 12 Power BI dashboards created and added to BEXEL CDE
• Over 30 video clips were created and used for the final showcase video