Maybe it's because I'm a bridge engineer, but I'm more interested in the connection structure between girders and columns than the scene of a vehicle crashing into a bridge. #bridge #engineering #civil #design #construction

Sai Krishna Sajja

Occupational Health, Safety & Environmental Professional | 10 Yrs Exp. in Infra Projects | Grad IOSH | M.Tech | IDIP. OSHMP | PSM | ISO 45001 | RAMS | RSO | IGC.

9mo

The problem arises from the transport agency's failure to conduct a route survey before transporting the Boom Placer unit. Height restrictions vary across locations, with some areas having a clearance of 5.5m and others limited to 4.5m. It is imperative to establish consistent height clearance throughout the route. Particularly in this incident Height restriction signage is missing. Luckily no one got injured expect the property damage.

Richard M.

Snr Project Manager - Marine & Structures. Capital & Renewals

9mo

Rare to see a 'Bridge Bash' take it completely off the bearings! Only a footbridge I presume? Agree with the other comments - where was the 'Over Dimensional Route' planning and clearance signage on this one? The Insurance Claim forms are always an entertaining read. "I was just driving along...." 🤣

Sanghee Jeon 전상희

CEO of 4MBiz at Global Clean Energy Sector BD & Consulting, Marketing, Trading at Free Agent 《AFE Global Partners | ENCLEA | EgyExport | POTENT | GRAWINDY | JUNNO Energy | LiFe Younger》

9mo

Beomsoo Park, It's because of an occupational disease 😅

Sanjeev Gupta (PMP®)

Vice President and Country Head, Larsen and Toubro Ltd

9mo

Girders are placed on bearings and the vehicle momentum has to overcome only friction, not the full weight. This is why we always keep about one to 3 feet margin while calculating headroom. This is not a structural issue:

Kamel Arbi

PhD, Sr. Material Scientist/Chemist/Concrete technologist/Expert in green/low-carbon cement, concrtete durability & innovative building materials/Committee Member @ RILEM Assoc. & the European Federation of Corrosion.

9mo

It seems that all the blame lies with the driver and those who have planned the route for his trip...and I also agree with that...but is it normal for a bridge to fall so easily? In most cases, structural engineers consider only the vertical load but rarely give the necessary importance to other types of loads.

Like
Reply
Anand Krishna

LinkedIn Top Voice in Construction & Civil Engineering || Planning & Project Controls || Contracts Administration & Delay Analyst || Civil Infrastructure technique Trainer || Getting Academia Industry ready

9mo

The traffic flow considerations and vehicular type has not been considered before constructing this bridge .In construction little ignorances may cause serious disasters.

Elí Torres

Más minería, más negocios!

9mo

Algunos tienen algunos años de experiencia y creen que nadie les podria aconsejar. Hacen el trabajo asi porque dicen "nunca sucedió"

CHIDAMBARA RAO KONDA

Assistant Manager ( Sr OHSE Manager ) CMRL 🚇

9mo

Prior to it , Goal Post / Height Barriers should be Provided with Proper Signages

Like
Reply

Road height restriction barrier 🚧 should have been constructed before entering the foot bridge. This could result in fatalities. The highway authorities must be vigilant on this.

Like
Reply
SATYENDRA KUWAR

Section Engineer at Central Railway (Pune Division)

9mo

Height gauge with 30cm below bottom of bridge girder or slab on both sides of the bridge should be provided.