Watch the progress of our Alexandra Park project in Toronto! cc: SvN Architects + Planners

View organization page for Tridel

40,022 followers

Construction at MRKT Alexandra Park is progressing well! Structural forming and "top off" were completed at the end of June. The precast façade is set to finish by the end of August, with windows being installed on Level 12. Inside, drywall framing is advancing on Level 4, and mechanical and electrical rough-ins are underway on Level 3. To read more & see progress from our on-site construction feed, visit https://bit.ly/42cu4LZ.