ANALYSIS OF METHODOLOGIES FOR COMPENSABLE EVENTS UNDER NEC 03 CONTRACTS IN CONSTRUCTION PROJECTS IN PERU
Abstract
In the context of construction projects in Peru governed by NEC 03 contracts, managing compensable events presents significant challenges, especially when discrepancies arise between the Employer and the Contractor regarding the analysis methodology to be employed. This article examines a specific scenario in a riverbank defense construction project where difficulties are encountered in evaluating compensable events that have either concluded or are ongoing. It analyzes retrospective and prospective methodologies, proposes appropriate approaches for each situation, and complements the analysis with insights from internationally recognized experts, aligning with the principles of NEC 03 contracts and international best practices.
Introduction
NEC 03 contracts have been adopted in Peru to enhance efficiency and collaboration in construction project management. However, practical application can present challenges, particularly in evaluating and managing compensable events that affect the project's schedule and costs.
This article addresses a scenario where the Employer and the Contractor disagree on the methodology for analyzing compensable events. While the Employer proposes a retrospective analysis without specifying the methodology, the Contractor advocates for a prospective analysis, respecting the proactive and collaborative spirit of NEC 03 contracts.
To enrich the analysis, summaries of articles by internationally recognized experts are included, providing insights into the methodologies they propose for similar cases.
Scenario Context
In a riverbank defense construction project under an NEC 03 contract in Peru, the following situations arise:
Given this situation, it's essential to define criteria and methodologies that allow for an objective and fair analysis of compensable events, facilitating an agreement between the parties.
Principles of NEC 03 Contracts
NEC 03 contracts are founded on principles of:
Situation Analysis
Using the data date from the last approved schedule, prior to the impacts, may not reflect the actual conditions during the events. It's advisable to update the data date to the moment immediately before the compensable event's onset.
Removing previously approved lags and logical relationships affects the schedule's integrity and can distort the analysis. Modifications should be consensual and documented.
The absence of a clear methodology for retrospective analysis creates uncertainty and may lead to subjective results. It's crucial to agree on a recognized and accepted methodology.
Proposed Analysis Methodologies
To address the presented challenges, specific methodologies are proposed for compensable events that have concluded and for those whose impacts have not yet ended.
A. Methodology for Concluded Compensable Events: Adapted Retrospective Impact Analysis
1. Establish a Reliable Baseline Schedule
2. Update the Schedule to the Point Before the Event
3. Incorporate the Compensable Event into the Schedule
4. Analyze the Event's Impact
5. Documentation and Support
6. Joint Review and Approval
Advantages of this Methodology
B. Methodology for Ongoing Compensable Events: Prospective Time Impact Analysis (TIA)
1. Establish an Updated Baseline Schedule
2. Identify and Document the Event
3. Update the Schedule to the Data Date
4. Incorporate the Event into the Schedule
5. Analyze Potential Impact (Prospective Analysis)
6. Evaluate Mitigation Options
7. Communication and Collaboration
8. Continuous Update
9. Formalization of Agreements
Advantages of this Methodology
Clarification on Prospective Analysis
In Proposal B, after the data date, a prospective analysis is conducted. Since the compensable event's impacts have not yet concluded, projections are made on how they will affect the project's future. This approach allows for anticipating delays and planning mitigating actions, in line with the proactive principles of NEC 03 contracts.
Insights from Internationally Recognized Experts
To further support the proposed methodologies, insights from internationally recognized experts in construction delay analysis and contract management are summarized below.
1. Society of Construction Law (SCL) Delay and Disruption Protocol
2. AACE International Recommended Practice No. 29R-03 (Forensic Schedule Analysis)
3. Dr. Keith Pickavance
4. James Zack and Ted Trauner
5. Dr. H. Murray Hohns
Implications for the Analyzed Case
CONCLUSION
Effective management of compensable events in projects under NEC 03 contracts requires applying analysis methodologies that are objective, transparent, and aligned with contractual principles. Incorporating insights from internationally recognized experts strengthens the proposed methodologies and underscores their validity.
Whether for concluded events or ongoing ones, it's essential for the Employer and the Contractor to collaborate closely in evaluating impacts and agreeing on solutions. The methodologies proposed—Adapted Retrospective Analysis and Prospective Time Impact Analysis (TIA)—offer structured frameworks consistent with expert recommendations and industry best practices.
Final Recommendations
By adopting these methodologies and recommendations, parties can strengthen their contractual relationship and contribute to the project's success, respecting the collaborative spirit and mutual trust characteristic of NEC 03 contracts.
References
This article aims to provide a technical and professional perspective on managing compensable events in construction projects under NEC 03 contracts, offering practical tools and methodologies to facilitate agreements between involved parties, enriched by insights from internationally recognized experts.