BOP - LOWERING PROCEDURE
Source: GE Oil & Gas

BOP - LOWERING PROCEDURE

  • Pressure test of BOP is performed up to their rated working pressure.
  • The BOP stack must be in perfect working order when lowered.
  • Surface & BOP mounted accumulator bottles are to be pre-charged with Nitrogen to the calculated pressure.
  • Prior lowering install guide lines in guide postes.
  • Connect the riser, hanging from the hook to the BOP.
  • Mount the riser angle beacon above the flex joint.
  • Pressure test choke, kill booster & hydraulic lines to recommended test pressures.
  • Carryout function test on both yellow pod & blue pod.
  • Check all function are in block position.
  • Switch hydraulic power unit to block position.
  • Disconnect junction boxes on hose reels.
  • Increase guideline tension to 8000 lbs.
  • Check the tensioner's bottle pressure is at calculated value.
  • Stand by bottles to be at max press.
  • Hoist BOP stack assembly with the travelling block.
  • Open spider beams & lower the BOP stack & continue lowering by adding riser joints.
  • As each riser joint is added pressure test choke, kill & booster lines.
  • Keep fitting pod hose clamps to the pod hoses & pod lines during BOP lowering.
  • Connect telescopic joint (collapsed) to the last joint of riser.
  • Lower telescopic joint and land it on spider below seal assembly.
  • Add one dummy riser joint and slowly lower the assembly to the support ring.
  • Actively lock down dogs (Rotating dogs) of support ring.
  • Move slightly up and down to check that dogs are well in place.
  • Unlatch blocking dogs.
  • Slowly lower the assembly.
  • Check riser tensioner pressure to carry all weight of string minus 20 T.
  • Hoop up kill, choke, booster and hydraulic lines.
  • Open the D.S compensator at 20 T.
  • Continue BOP lowering monitoring the approach towards guide posts by ROV.
  • Stop descent about 2-3 meters from guide posts according to heave conditions.
  • Check hook load and lower stack carefully on wellhead while monitoring the ROV.
  • Position the stack firmly and activate BOP wellhead connector to "lock".
  • Perform pick up test by over pulling up to 20-25 T by means of compensator.
  • Check all riser tensioner pressure.
  • Open inner barrel & rest on spider and disconnect dummy riser.
  • Make up diverter on inner barrel and install in rotary.
  • Connect all hydraulic lines and break out diverter running tool.
  • Decrease guide line tension to 4000 lbs.
  • Carry out diverter operational check.