Expected Claims from Design or Engineering Consultants

Expected Claims from Design or Engineering Consultants

Claims from consultants are not uncommon and can arise from various factors such as scope changes, delays, or miscommunication. These claims, if not managed proactively, can lead to disputes, project delays, and cost overruns. Below is a detailed examination of the types of claims typically raised by design and engineering consultants, their causes, examples, and strategies for mitigation.


1. Scope Creep or Additional Work Claims

Description: Scope creep occurs when the consultant is required to perform work that goes beyond the agreed scope of services outlined in the contract. This often results from evolving project needs, unclear initial specifications, or client requests for additional deliverables without formal change orders.

Potential Causes:

  • Poorly defined project scope at the outset.
  • Changes in project objectives or specifications by the client.
  • The need for additional studies or design iterations due to unforeseen challenges.

Examples:

  • A client requesting a redesign to accommodate additional floors in a building.
  • Performing extra feasibility studies or alternative designs due to changes in the project brief.

Impact: Increased workload, higher resource utilization, and delays in delivering other contracted tasks.

Mitigation:

  • Clearly define the scope of services and include provisions for change orders.
  • Regularly review the scope with the client to address potential changes early.
  • Document and approve all additional work before commencing.


2. Delays in Design Approval or Input

Description: Consultants often rely on timely input and approvals from clients or other stakeholders to proceed with their work. Delays in these processes can disrupt the consultant's workflow and result in claims for time and cost compensation.

Potential Causes:

  • Prolonged review cycles by the client or project management consultant (PMC).
  • Delayed provision of critical project data, such as site surveys or soil investigation reports.

Examples:

  • A project stalled due to delayed approval of a preliminary design report.
  • Waiting for key performance requirements to finalize detailed engineering.

Impact: Disruption in resource planning, increased overhead costs, and potential delays to the overall project timeline.

Mitigation:

  • Set clear deadlines for approvals and inputs in the contract.
  • Establish escalation procedures for delayed responses.
  • Use digital platforms to streamline design review and approval processes.


3. Claims for Delay or Disruption

Description: External factors, such as site conditions, sequencing changes, or unforeseen challenges, can disrupt the consultant's progress, leading to claims for additional time or costs.

Potential Causes:

  • Unanticipated site conditions requiring changes to design assumptions.
  • Modifications in the construction sequence necessitating out-of-turn design deliverables.

Examples:

  • A consultant being asked to accelerate deliverables due to construction schedule changes.
  • Revising structural designs after discovering geological issues during excavation.

Impact: Reallocation of resources, increased pressure on teams, and cost escalations.

Mitigation:

  • Conduct thorough pre-design studies and risk assessments.
  • Align the consultant's schedule with the contractor’s construction plan.
  • Include provisions for disruption claims in the contract.


4. Rework Due to Changes

Description: Rework claims arise when completed designs need to be revised due to changes in project specifications or external factors. This is a common source of friction between consultants and clients.

Potential Causes:

  • Late-stage changes requested by the client or other stakeholders.
  • Regulatory or code revisions impacting previously approved designs.

Examples:

  • Modifying HVAC designs to incorporate additional energy efficiency measures.
  • Adjusting structural designs after new seismic standards are introduced.

Impact: Increased workload, wasted resources, and potential delays in delivering other milestones.

Mitigation:

  • Clearly define procedures for handling changes in the contract.
  • Regularly engage with stakeholders to anticipate potential changes.
  • Incorporate design flexibility to accommodate minor adjustments without extensive rework.


5. Claims for Intellectual Property or Copyright

Description: Consultants may file claims if their proprietary designs, software, or methodologies are used without authorization or proper compensation.

Potential Causes:

  • Use of consultant-provided designs in future projects without agreement.
  • Misappropriation of proprietary tools or intellectual assets.

Examples:

  • A client reusing engineering drawings for another project without approval.
  • Unauthorized sharing of proprietary design software or methodologies with third parties.

Impact: Legal disputes and potential reputational damage.

Mitigation:

  • Include clear intellectual property clauses in contracts.
  • Specify ownership rights for deliverables and permissible uses.
  • Monitor usage of proprietary designs or tools post-project completion.


6. Cost Escalation Claims

Description: Prolonged project timelines can lead to increased operational costs for consultants, which are often not accounted for in the initial agreement.

Potential Causes:

  • Delayed project timelines due to external factors.
  • Inflation or unforeseen cost increases during extended project periods.

Examples:

  • Increased staffing costs due to prolonged involvement in a delayed project.
  • Escalation in software licensing fees required for ongoing design work.

Impact: Reduced profitability for the consultant and strained client relationships.

Mitigation:

  • Include escalation clauses in contracts to address inflation and extended timelines.
  • Regularly monitor project schedules to identify potential delays early.
  • Negotiate revised fees for prolonged engagements.


7. Claims for Non-Payment or Delayed Payment

Description: Non-payment or delayed payment of invoices for completed work is a common source of claims from consultants.

Potential Causes:

  • Disputes over the quality or scope of completed work.
  • Administrative delays in processing payments.

Examples:

  • A client withholding payment for design deliverables pending dispute resolution.
  • Delayed milestone payments due to internal approval bottlenecks.

Impact: Cash flow issues for the consultant and reduced project morale.

Mitigation:

  • Clearly define payment terms and milestone criteria in the contract.
  • Include provisions for interest on delayed payments.
  • Maintain detailed records of completed work to support payment claims.


8. Professional Liability or Indemnity

Description: Consultants may face claims arising from alleged professional negligence or substandard work, leading them to file counterclaims for indemnity or dispute resolution.

Potential Causes:

  • Errors or omissions in designs leading to cost overruns or safety concerns.
  • Disputes over interpretations of design intent.

Examples:

  • A contractor blaming the consultant for construction delays due to unclear drawings.
  • Claims of inadequate structural design leading to additional reinforcement requirements.

Impact: Legal costs, reputational damage, and potential financial penalties.

Mitigation:

  • Maintain robust quality control processes.
  • Carry professional indemnity insurance to cover liabilities.
  • Ensure designs are peer-reviewed and comply with all relevant codes and standards.


9. Force Majeure or Unforeseen Events

Description: Claims may arise when disruptions caused by unforeseen events like natural disasters, pandemics, or geopolitical crises impact the consultant’s ability to perform.

Potential Causes:

  • Restricted access to project data or sites.
  • Delays in resource availability due to global supply chain disruptions.

Examples:

  • Postponed design reviews due to pandemic-related restrictions.
  • Inability to conduct site visits following a natural disaster.

Impact: Missed deadlines and increased costs.

Mitigation:

  • Include force majeure clauses in contracts.
  • Develop contingency plans for remote working and digital collaboration.
  • Adjust project schedules to account for delays caused by external events.


10. Claims Arising from Coordination Issues

Description: Misalignment or poor communication between consultants and other project stakeholders can lead to inefficiencies and claims for additional time or costs.

Potential Causes:

  • Lack of clarity in roles and responsibilities.
  • Miscommunication regarding project requirements or timelines.

Examples:

  • A design consultant revising drawings multiple times due to conflicting inputs from the contractor and client.
  • Errors in integrating third-party designs with the consultant’s work.

Impact: Frustration among stakeholders, increased workloads, and delays in project delivery.

Mitigation:

  • Establish clear coordination protocols and communication channels.
  • Appoint a dedicated project manager to oversee coordination efforts.
  • Use collaborative tools to ensure alignment across all stakeholders.




David Cimino

Contracts & Commercial Management

2w

Well condensed, as usual. Many thanks

Like
Reply
Vipul Tank

Document Controller & Information Management Specialist | L&T || Ex-AECOM || Ex-Adani || Ex-Cairn India/Vedanta || Ex-NMSEZ || Ex-RIL

3w

Ilamparithi BoologaSundaraVijayan Sir, Insightful article! Proactively managing claims is indeed crucial to avoiding disputes and ensuring project success. Clear communication, well-defined scopes, and collaborative problem-solving can make a significant difference in mitigating risks. Thanks for sharing these valuable strategies!

Zarex Robas

Strategic Contract Management, Digital transformation, Change management, Agile project delivery, PMO, Strategy planning, Research synthesis

3w

You have a similar discussion relating to the Project Management Consultant.