How can we use the CMMS to help us make Repair/Replace Decisions?
At its most basic level, you must first compare the equipment’s value to the repair cost you would repair the equipment when the repair cost is less than the equipment’s value. Or, you would replace the equipment when the repair cost exceeds the equipment’s value.
Knowing when to stop holding equipment and replace it has always been challenging. Holding onto underperforming equipment can cause increased downtime, greater risk of accidents (assets and personnel), labor costs, and production delays.
Repair/replace criteria is an advanced process which if proceduralized, adds value to any size organization. Many believe, that if the repair cost is <= 50% of the replacement cost, and the equipment's life-cycle expiration is 50% or lower of its expected life-cycle, the equipment will be repaired. But I would be wary of basic rules of thumb.
There can be many other factors to consider when making repair/replace decisions, such as service history, dependability, maintainability, operability, cost to repair, age, active warranty, remaining lifetime, manufacturer out of business, excessive lead-time on parts, technical manuals not available, and the cost of downtime.
Ask the Reliability Team to Create a Set of Questions by Asset Class
You can be as creative as you need to be to make an accurate decision.
Other Thoughts from Industry Professionals
[Answer #1] If a cost estimate is made on the sum of all pump replacement pieces, e.g., volute, wear plate, impeller, bearings, etc. the costs (without labor) can be several times more than a complete brand new, replacement pump of newer design. But will the property department responsible for CAPEX vs OPEX decisions be “okay” with the decision to buy new pumps?
[Answer #2] Economics often drives the repair/replace decision. The most important is production. The option that provides maximum availability might be the best choice. Any increase in availability will far outweigh the repair/replace cost. If the asset takes longer to repair than replace and the production output is more than the repair (and replace is quicker), then replacement is the best option.
[Answer #3] The Asset Manager should acquire Replacement Asset Value (RAV) for every asset. Regarding repair/replace analysis, the asset should be replaced if the annual running costs (ARC) exceed the value, e.g. ARC > 0.02 x RAV (i.e. > 2%). But because money is not all, the trade-off ARC - availability - reliability - risk is in my opinion the key.
[Answer #4] I would run a SQL query against the CMMS database that pulls 3-5 years of history to calculate asset cost-effectiveness by dividing the AVERAGE ANNUAL MAINTENANCE COST by REPLACEMENT COST. If this answer is greater than 7% then "this asset is in trouble" and deserves deeper analysis by the reliability team:
Recommended by LinkedIn
Develop a Formal Repair/Replace Procedure and Process
The ideal repair/replace analysis relies on objective data captured from the CMMS. As a matter of protocol, the maintenance supervisor (and/or reliability engineer) would be involved in the final justification before this information is then taken to the maintenance manager for approval.
In the Old Days
A maintenance supervisor would simply walk into the maintenance manager's office and say, “We need a new asset.” After a short discussion, a purchase requisition would be initiated.
How do you Know when a Repair/Replace Discussion is Needed?
A Prebuilt Checklist May Help
Without the Above, Finance May Take Charge
This link will go to a LinkedIn post that explains this calculation: Equivalent Annual Cost (or EAC).
Engineer Manager
7moModernization and standardization for compatibility with the rest of the plant is a key decision factor in my environment. Example, one utility switchgear operates perfectly well but requires different maintenance tasks, spares, vendors to overhaul, and cannot be added to SCADA.
Gerente de Engenharia de Manutenção | Bram Offshore
8moJoão Paulo Vilvert Guilherme Chiminelli
This is a good example; I hope it is in the book!
Mechanical Engineer | Material Cataloguer | CMMS | Maximo| VCAT1 |
8moVery informative post. This will aid in analyzing and making decisions as to repairing or replacing a piece of faulty equipment, hence reducing maintenance costs.
MBA Management Strategy (Namibia Business School); Masters Industrial Engineering (NUST); B Tech Mechanical Engineering (CPUT); SMDP (USB)
8moVery good read, thank you.