How to Quantify Prolongation Costs
It's often the case that claimants derive prolongation costs by determining an average daily rate taken from the preliminaries and/or indirect costs listed in the contract and multiplying that rate by the number of days delay.
A claimant must firstly identify the actual days of delay a respondent is culpable.
The appropriate method to identify actual days of delay is to complete a cause-and-effect delay analysis.
Next, the claimant's actual days of delay need to be identified to quantify the costs incurred on those days. Finally, the claimant should then analyse its cost records relating to the periods of delay, which are the respondent's responsibility.
Prolongation costs must reflect the actual losses incurred by a claimant unless otherwise stated in the contract.
To demonstrate a causal link and substantiate the cost claimed, the claimant should reconcile records of the indirect and direct costs such as daily reports and/or timesheets to the days claimed. In addition, the claimant can put forward other records such as invoices, etc., if they can be proven that they are recoverable.
Separate into direct and indirect costs
Assuming actual days of delay have been identified and the actual costs have been quantified and separated into indirect and direct costs. The claimant is also required to evidence that the costs claimed were on the project.
Substantiation in the form of (but not limited to) daily progress reports, daily diaries and sign in/out registers is required.
Without this type of contemporaneous evidence, it would be difficult for a claimant to prove the costs they are claiming were related to the delay event(s).
Indirect Costs
Generally, the claimant can claim only time-related indirect costs incurred during the period(s) of delay identified and costs can only be claimed for the days that are not the claimant's culpability. These costs typically include staff salaries, insurance costs, bank guarantees and reoccurring site running costs. The claimant cannot include purchase costs or capital costs such as vehicles, plant and office equipment.
Recommended by LinkedIn
Direct Costs
Direct costs that the claimant can claim are those direct costs that naturally flow from the identified delay events. It is reasonably straightforward to work out the direct cost by reviewing an as-built program that demonstrates what direct costs were on the critical path at the time of the delay. Records such as timesheets, sign in sheets and payroll data will provide evidence the direct costs were incurred during the delay period.
The key points to remember when quantifying prolongation costs are as follows:
If you enjoyed this LinkedIn Managing Construction Claims newsletter, I would love it if you subscribed for more, let me know your thoughts, or shared with your network.
To learn more about managing claims or how Accura Consulting can help you, head to our website or get in touch.
--
Paul
Resident Engineer at F&M Middle East @PMI-ACP@MEng
9moProlong cost contractor cliam only after approval of EOT ? if the client not Agreed for EOT then whats the next move contractor can do ??
JASARA PROGRAM MANAGEMENT COMPANY | Riyadh, Saudi Arabia April 2024 - Present
9moThere are always compensable delays and non compensable delays. The claimant can’t ask for prolongation costs when he is also delayed. This is called a concurrent delay. This delay is not compensable to the claimant and can’t be considered as part of the prolongation cost claim.
Principal Mentor/Trainer at ICL Academy. Construction Dispute & Claims Specialist for FIDIC 1999 & 2017, Malaysian Forms - PWD 203A, PAM 2017 and other Standard Forms- JCT, NEC, SIA (Singapore) etc.
9moOne question that always I cannot get my head around it - This is Head Office overheads are Indirect costs that cannot be determined to any acceptable level. So why is so many Claims Professionals are using all sort of methods to prove it. Somany ways to do it and worst is all will give different results making it undeterminable. !!!!!