It attributed the delays in signing PPAs to factors such as lack of clear directions, prolonged internal
approval process, involvement of multiple ministries after finalization of tenders.
To address this, it had recommended to establish a single window system to minimize the complexities of internal approval process reducing the involvement of multiple ministries.
Further, the committee had also suggested the Ministry to collaborate with agencies to develop
standardized model formats for PPAs and fix definite time period for various levels of approval.
It urged the Ministry to make all out efforts to address the systemic challenges and ensuring that the mechanism in place have a direct and measurable impact on the solar park development
project.
Regarding the issue of Great Indian Bustard area where projects have been delayed because of wildlife concerns, the committee said it feels that the ministry should not just await the implementation of the expert Committee report on the subject but also actively explore and implement interim mitigation measures, such as installation of bird diverters on existing power lines, to minimize risks to the Great Indian Bustard population.
(Catch all the Business News, Breaking News, Budget 2024 Events and Latest News Updates on The Economic Times.)
Subscribe to The Economic Times Prime and read the ET ePaper online.
Read More News on
(Catch all the Business News, Breaking News, Budget 2024 Events and Latest News Updates on The Economic Times.)
Subscribe to The Economic Times Prime and read the ET ePaper online.