Congratulations to the entire Project NEXT team for a successful 'Big Beam' weekend! From Friday night to early Monday morning, crews detoured the northbound lanes of the I-495 Beltway and safely erected 5 rows of girders for a future ramp. Spanning 295 feet and consisting of 10 beams, each girder was over 11 feet tall and 3 feet wide and weighed between 70 and 80 tons. This could have only been successful through the detailed planning, coordination and cooperation of a lot of dedicated and hardworking individuals. Special thanks to each and every construction team member, High Steel Structures LLC, The Lane Construction Corporation, Virginia Department of Transportation, Transurban, Virginia State Police, Metropolitan Washington Airports Authority, and of course the public for doing their part to avoid the area!
-
-
-
-
-