As 2024 draws to a close, we’re excited to report continued progress at the Martin and Horning solar project sites. Thanks to the dedication and expertise of our Engineering and Project Management teams, along with the diligence and experience of our EPC contractor, EnSiteUSA, construction on both sites remains ahead of schedule. With all solar modules installed and wiring well underway, we are now focused on completing the transformer foundations and inverter installations - key steps as we move closer to energizing these projects. Looking ahead, we are on track to wrap up construction in 2025, bringing these sites fully online to contribute to New York State’s renewable energy goals. We look forward to building on this momentum in the new year as we continue our commitment to creating a more sustainable world through the advancement of clean energy.