Safe Lifting Operations’ Post

Tandem lifting with cranes can be useful for lifting heavy objects or structures that are too large or heavy to be lifted by a single crane. ⚠ When the load is too heavy for a single piece of equipment, two cranes can safely distribute the weight. ⚠ When the load is too long or too wide, two cranes can provide anchor points that stabilize the load and prevent dangerous load swings. The crucial aspect of this type of operation is the simultaneous operation of the two devices. What are the factors to check while using the tandem lifting method? 1. You have to determine the center of gravity of the load before you attempt to lift the load. 2. The cranes' positions matter when lifting a huge load using the tandem method. 3. Sideloading must be avoided during tandem lifting/single lift. 4. Weight distribution is another factor we must consider while performing tandem lifts. 5. Wind speed, ground support, etc 6. A Qualified Lifting Plan must be approved and socialized to people involved in lifting operations. Any feedback from you all regarding this lifting plan? Let's review and learn together and have a great weekend! - DAS - #safeliftingoperations #tandemliftingoperations

Rodney Fermin

Crane Operator/Rigger/Dogman at Smith Crane and Construction Limited

7mo

The sharing of load calculation can also be a great addition to the tandem lift. Where the higher capacity crane hook block can be located either halfway to the c of g of the load depending on the length of the load to be lifted, while the smaller capacity crane hook block will be at the end tip of the load. In this instance, the smaller crane can gain more lifting capacity and stability roughly up to 50% of lifting capacity.

Peter Verhoef

Consultant - specialist dedicated to (heavy) lifting, hoisting, rigging and specialised transport.#cranes #knowledge #consultancy

7mo
Aldo Gonzales Montoya 🇵🇪

Heavy Lift Coordinator|Site Lifting Specialist, Lifting Equipment | LEEA APLO

7mo

Additional about GBP for ground preparation and UG if have any pipe, electrical cable or manholes, is very important make ensure if for both crane have enough capacity, communication same language from signalman for both crane operators. Thank you for share information 😊.

Arsath Risvi BE, ME Struct, C.Eng(I), AMIE

Senior Structural Engineer/مهندس إنشائي - مدني

7mo

How do you account for the additional stresses that occur in the lifting element due to the difference in the coordination of the cranes in vertical direction during lifting and in horizontal direction during slewing of cranes? Is there a codal standard that speaks about the additional factors to be considered during the above additional stress calculation of the lifting element?

Mahmood AL_Salih

Lifting & Hoisting Supervisor BGC (Shell Join Venture) | NPORS & LEEA Quilified | Engineer

7mo

Rule of thump, whenever you get chance to avoid the tandem lift, just avoid it? As control, its preferable to use the same crane manufacturer for both cranes and models where applicable and that's will benefit you in setting up the movements speed and the winches speed in the same degree 😀 Too many things here need to be thought and determine before you go with this option

David Stockman

Silamas Group Thailand Technical adviser

7mo

Your intentions are with good intentions However the liebher info is not correct and believe your possible using 85% duty charts Weighing of loads to establish C of G Knowing a load weight and lifting points calculations to establish crane capacity Lifting plans, method statements JSA are approved by client and returned to subcontractor to work to.

AGBEKO KOMI AVOSSE

Experience in Liebherr Telescopic .Liebherr Crawler K 3290 ( MRC 300 Tns All Terrain Cranes*Crawler Cranes, Kobelco,Terex ,all types of cranes .Seeking new opportunity and speak English & French

7mo

TANDEM Lifting Everyone to know what were going to do First and Next and teamwork The Leader would task to the team two (2) Cranes Operator's, (1)Rigger and the Helpers before Lifting start

Hamid Butt

Head of Board @ Lifting and Rigging Equipment Supplier

7mo

Happy Coal Miner's Day! Let's raise a pickaxe (or a cup of coffee) ☕️⛏️ to these amazing folks who power our world! #ThankYouMiners #CoalMinersDay

Sanjay Mishra

Lifting Superintendent at Tecnicas Reunidas

7mo

Crane 🏗️ 2 main block not in right vertical.

Nweze Eberechi Nicholas

Senior Technical Training Instructor on Lifting Operations | hse Trainings (B.Eng, Nebosh IGC3, Train the Trainer with the Knowledge academy) UK, Petroleum and gas engineering, University of Port Harcourt

7mo

In addition to your factors, there should be appropriate planning and adequate supervision by a competent person to ensure the Lifting operation will be carried out in safe manner & this should be done in accordance with LOLER Regulation 8!

See more comments

To view or add a comment, sign in

Explore topics