Does your cost breakdown structure match your work breakdown structure in your project?
In a lot of projects, both do not always match and the following are some reasons why:
- Planners/Schedulers are often mobilised later on a project. Most times at the project start, high-level schedules with few lines are usually enough for stakeholders
- Cost is always deemed more important than Schedule. Repeating what I said in number 1, most times at the project start, high-level schedules with few lines are usually enough for stakeholders but cost estimation attempts to be as detailed as possible even from conception. We tend to forget that time is money.
- Where the planning/scheduling team is mobilised early, the different project teams including scheduling and cost teams begin working independently/ in silos caused by:
- the need to meet up to complete the overall project planning as fast as possible. Planning here means developing plans including scheduling, cost budget, quality plans, etc.
- Lack of team synergy and integration.
4. For most contractors, the cost model and CBS are handed over to them by the client in the contracts in the form of payment structures: that is what the contractors tend to mirror.
- Cost loading of detailed schedules becomes difficult.
- Overall/Integrated project monitoring and controls become challenging: costs are skewed away from the schedule.
- Of course, performing EVM becomes tough with unrealistic results.
- Performing integrated schedule cost risk analysis becomes challenging. Though most QRA software like Deltek Acumen, Safran, etc. try to make it easy to map your costs from whatever format and arrangement it is to your schedule but it is not usually effective. Here is my experience, a lump sum cost estimate consists of estimates for 2 different activities with two different WBS but the lump sum was not broken down in the original estimate document/software. The solution can be to tell the estimator to break it down but there are thousands of them and unseparated actuals have been implemented on them.
- Most importantly, when delays, extension of time and need for recovery, it becomes hard to align and realign the project.
- One I have personally experienced, it becomes difficult to synchronize your cost and schedule on your project management tools. I wanted to synchronize approved cost on SAP with the baseline schedule on Primavera P6 and it was nearly impossible.
- The out of sync between WBS and CBS can even affect your Integrated reporting whether Excel or Power BI. Each one's values and charts will be speaking out of tune with the other on the dashboards
Just like Primavera P6's schedule, everything looks fine on the schedule at the beginning but when you start updating, the schedule may start looking strange due to all your own chosen default settings and set-up.
Therefore, let your schedule meet your cost closely by matching your WBS with your CBS as early as possible. Both should have similar nomenclature or names and ID/numbering, it will pay you down the road!
Overall, all your project plans: schedule, cost, risk, quality, procurement/supply chain, HSE etc. must match and be integrated together for a seamless project success.
What challenges have you faced not matching CBS with WBS?
Have you resolved such challenges before?
Senior project Control Specialist (Planning and Scheduling )
6dOne of the major reasons why the CBS won’t be matching with the WBS. 1. The progress measurement system: the planning team measure progress using the level of effort earned for example the weightage system can be 5% for engineering 20% on procurement 70% on construction and 5% on close out /TC. This will give a balanced scurve because we all agreed that’s more effort is spent during the construction phase. But the CBS isn’t structure in this way when you procure a material like the HVAC system you need to claim the funds from the client and as a result the weightage system for planning dept and commercial department can never be same. If the planning department consider high weightage for procurement because more money is spent during the stage then the schedule will be considered as a front loaded schedule because there will be a huge progress once all procurement has been done without completing the installation/ construction. There are several reasons why the CBS and WBS can not be same. It’s can be closely related but it cant be same
Database Admin - SCM & Scheduler / Planner - Oxy GoM
6dGreat article and I do believe that the cost of scheduled should line up. Although I think a lot of people make it harder than what it truly is. If you build your schedule the way you do your work, then build a code structure the way your cost structure is, you can just code out the activities where they fall in the cost structure. Then you have the ability to flip it either way that you want it. You can see the cost based on the structure that your company has, or you can flip it and look at the work based on how you're doing your project. Don't make it harder than what it should be, it's easy to align and work with if you use a little bit of thought. The great thing about using a code structure that way, you can have multiple projects open and look at things all the way across the board.
Administrative Assistant| Administrative Officer | Data Analyst Enthusiast| Financial Analysis Enthusiast
1wA very interesting one!
Great article! Problem with many projects these days. Apart from the disadvantages mentioned in your article, planning team has to monitor and control cost and time separately which becomes a hectic job throughout the project lifecycle.
EPC Project Planner |Quantitative ( Scheduler & Cost ) Risk Analysis| Mechanical Industrial Engineer Specializing in Oil and Gas Installation and Dismantling | Chemical Technician| Steam Generation Operator
1wInteresting