Getting the Measure of Disruption | Disruption vs Delay
Part One
Construction projects often result in cost overruns because of disruptions and delays created by the employer or contractor. This series of articles discusses aspects of disruption and identifies issues related to measuring disruption on Construction projects. The first article in the series identifies what disruption is and what is to be measured.
Introduction
Delay and disruption are often (incorrectly) referred to by industry practitioners as if they are one and the same. Although the terms “delay” and “disruption” are commonly used interchangeably, they are entirely separate issues that need to be addressed and measured separately. This article will review the relationship between delay and disruption and review the measurement of disruption, as distinct from delay.
What Is Disruption (As Distinct from Delay), and What Is to Be Measured?
Definitions
Disruptions prevent the contractor from completing work activities within its originally planned costs,[1] whereas delays prevent the contractor from completing the works within the originally planned duration. Delay claims capture the additional time (and associated time-related cost) due to the reduced rate of progress, whereas disruption claims capture the additional cost of completing the work activities.
Disruption is not delay; however, there may be a relationship between disruption and delay in that a contract that has been delayed will most likely have been disrupted, and both may have arisen from the same events. Further, delay and disruption can be interrelated, where disruption can contribute to causing delay or delay can cause disruption. In these circumstances, the Society of Construction Law (SCL) suggests that a contractor may undertake a delay analysis to support its claim for disruption.[2]
Recommended by LinkedIn
It should be noted that delays are generally measured by way of a programme analysis that focuses on critical path activities. However, a critical path analysis is unlikely to provide the basis for a realistic assessment of disruption because, typically, only 20 per cent of programme activities are on the critical path, whereas disruption can affect 100 per cent of programme activities.
Therefore, due to the differing components of disruption (cost) and delay (time) the effects should be analysed independently and rely on different analysis methods.
Disruption can be described as the disturbance to the regular and economic progress of the works,[3] which results in additional cost where labour or plant is underutilised.[4] This disturbance, or hindrance, interrupts the contractor’s normal working methods, resulting in lower efficiency.[5] Therefore, disruption is fundamentally about reduced productivity in the execution of work activities.[6]
Production & Productivity
When analysing disruption, it is important to distinguish “production” and “productivity.” Production is measured in units of work output (e.g., m2 m3 etc.) while productivity is usually measured as the units of production per unit of effort. It can be expressed as output divided by input (m2/man-hour) and alternatively, it can be expressed as input divided by output (man-hour/m2).
Productivity loss happens when a contractor is not accomplishing its anticipated planned rate of production,[7] where the contractor produces less than its planned unit of output per planned unit of input. Disruption is the measure of the loss of productivity between the contractor’s planned and actual rates of production.[8]
So, measurement of disruption equates to measuring productivity loss. Organisations like the Society of Construction Law (SCL) and the Association for the Advancement of Cost Engineering International (AACEI) recommend techniques to measure disruption which will be discussed further in the next article of this series.
References
Expert Delay Analyst & Quantum Consultant
2yI am anticipating the next set of articles on how the disruption cost is actually calculated. With the usual contracts only "costs" or "loss and expense" can be recovered so if the main contractor has not received a claim from his sub-co tractors it has not "cost" him anything. The NEC suite however allows the main contractor to "value" disruption whether it has cost him anything or not. I will be interested to learn how either cost or value is calculated in these different circumstances.