"Need of Delay Analysis in Construction Projects"
Delay analysis in construction claims is essential because any delay must impact the critical path, making it crucial to assess the effect of delays on project timelines.
Construction contracts typically specify that adjustments to critical milestones or scheduled completion dates are only warranted if the delay impacts a critical path activity. This aligns with industry norms, as outlined in the SCL Delay and Disruption Protocol 2nd Edition stating that "an EOT should only be granted to the extent that the Employer Delay is predicted to reduce to below zero the total float on the critical path affected by the Employer Delay to Completion (i.e. if the Employer Delay is predicted to extend the critical path to completion).”
Delay Analysis Methods:
Delay analysis can be performed by a few methods.
1. IMPACTED AS PLANNED ANALYSIS
The impacted as-planned analysis involves the insertion of delay events into a baseline or as-planned schedule to determine the hypothetical impact of such events. This method involves modifying the baseline or as-planned schedule to include new activities and logic to represent delay events. The difference between the project completion date in the impacted as-planned schedule and the original as-planned schedule quantifies the delay. This methodology is simple and does not require an as-built schedule. However, it is considered a hypothetical model as it does not rely on as-built data.
Steps to perform:
The resulting schedule, after inserting the impact event, illustrates the effect of the delay/change event on the project’s completion date.
2. AS-PLANNED VS. AS-BUILT ANALYSIS
It is a simple technique used to compare the baseline or as-planned schedule to the as-built schedule or a schedule update reflecting progress. This method compares planned start and finish dates with the actual start and finish dates of activities on the as-planned critical and near-critical paths. This identifies delayed starts, extended durations, and late finishes. This method is most effective on simple projects with short durations and one clear critical path that remains consistent throughout the entire project. Its accuracy diminishes as the actual critical path deviates from the planned schedule.
3. Time Slice Windows Analysis
Time Slice Windows Analysis is an observational, windows-based methodology that focuses on comparing as-planned, updated and as-built project schedules to identify and quantify delays to the critical path of the project.
This methodology is a retrospective analysis that uses the project schedule updates to quantify the slippage to the critical path during a select period of time.
Once all critical path activity delays have been quantified, the origins and causes of each delay are determined. The responsibility for each delay is then apportioned to either the Contractor, Owner, a third party, if appropriate, and to force majeure or other excusable delays defined by the contract.
Recommended by LinkedIn
Steps to perform:
4. TIME IMPACT ANALYSIS
Time Impact Analysis is a schedule delay analysis technique that adds delays or changes to the schedule which are updated up to the day before the delay occurred.
The Purpose of the Analysis:
Steps to perform:
5. COLLAPSED AS-BUILT / AS-BUILT BUT-FOR ANALYSIS
Collapsed As-Built Analysis is a retrospective schedule delay analysis technique that determines the earliest date that the project completion date, or a required milestone could have been achieved but-for the owner-caused / contractor-caused delays that occurred during the project.
The Purpose of the Analysis:
Steps to perform:
Administrative Clerk at Amazon
11moGreat article 👏