How to perform Time Impact Analysis / Window Analysis in Primavera P6
A Time Impact Analysis is a method used to determine extent of impact from potential delay in construction process. This schedule analysis method involves the insertion or addition of activities indicating delays or changes into an updated schedule representing progress up to the point when a delay event occurred to determine the impact of those delay activities.
Types of Delays
Delays can be categorized in two main areas:
Excusable delays occur when the affected party is allowed to claim for a time extension, compensation or both. Meanwhile, non-excusable delays are delays that the contractor or party affected will need to bear the responsibility.
We have a simple project with the Planned schedule like this:
1st month.
We have delay (21 days) on Excavation due to Unforseen site condition
2nd month.
We have no delay.
3rd month.
We have 2 delays:
And those are concurrent delay. So 14 days charge to owner, and 7 day charge to contractor
4th month.
We have 1 delay from Contractor in “Garage Walls” but it was not on the critical path. As long as the delay is within available float there is no effect on the final completion date.
5th month.
We have 1 delay (28 days) from Owner in Garage Doors but it only affect 7 days in the critical path. Other 21 days were absorbed by available float.
Last month.
We don’t have any delay.
So we can have the Time Impact Analysis report like this:
Thank you for your time to read this article.
DBA at International University
9moLaraib Fatima Dar (PMP)® thanks for sharing
Lead Planning Engineer at Parsons International Limited
2yHi, In the above analysis, the total number of EOT to be awarded is 28+14=42. And compensable Prolongation cost period is 28 days. Is this understanding correct