How to perform Time Impact Analysis / Window Analysis in Primavera P6

A Time Impact Analysis is a method used to determine extent of impact from potential delay in construction process. This schedule analysis method involves the insertion or addition of activities indicating delays or changes into an updated schedule representing progress up to the point when a delay event occurred to determine the impact of those delay activities.

Types of Delays

Delays can be categorized in two main areas:

  • Excusable Delays
  • Non-Excusable Delays

Excusable delays occur when the affected party is allowed to claim for a time extension, compensation or both. Meanwhile, non-excusable delays are delays that the contractor or party affected will need to bear the responsibility.

We have a simple project with the Planned schedule like this:

No alt text provided for this image
No alt text provided for this image

1st month.

We have delay (21 days) on Excavation due to Unforseen site condition

No alt text provided for this image
No alt text provided for this image

2nd month.

We have no delay.

No alt text provided for this image
No alt text provided for this image

3rd month.

We have 2 delays:

  • Owner change house design (14 days)
  • Subcontractor left job (21 days)

And those are concurrent delay. So 14 days charge to owner, and 7 day charge to contractor

No alt text provided for this image
No alt text provided for this image

4th month.

We have 1 delay from Contractor in “Garage Walls” but it was not on the critical path. As long as the delay is within available float there is no effect on the final completion date.

No alt text provided for this image
No alt text provided for this image

5th month.

We have 1 delay (28 days) from Owner in Garage Doors but it only affect 7 days in the critical path. Other 21 days were absorbed by available float.

No alt text provided for this image
No alt text provided for this image

Last month.

We don’t have any delay.

No alt text provided for this image
No alt text provided for this image

So we can have the Time Impact Analysis report like this:

No alt text provided for this image

  • 28 days for time and cost
  • 14 days for time

Thank you for your time to read this article.


Quantech Surveys

DBA at International University

9mo

Laraib Fatima Dar (PMP)® thanks for sharing

Like
Reply
Sudhir Akkatangerhal

Lead Planning Engineer at Parsons International Limited

2y

Hi, In the above analysis, the total number of EOT to be awarded is 28+14=42. And compensable Prolongation cost period is 28 days. Is this understanding correct

Satish Kumar - PRINCE2®, M.AAPE ,M.ASCE, M.AIB, MIET,

Planning Engineer/ Principal Planner AL RYUM GROUP OF COMPANY (Al Ryum Cont. & Gen.Transp. LLC)

3y

Thanks for sharing

To view or add a comment, sign in

Insights from the community

Others also viewed

Explore topics