How to remove the gap between actual bar and remaining bar in schedule update in Primavera P6

No alt text provided for this image

In the schedule update of Primavera P6, there is occasionally a gap (empty space) between the actual bar and the remaining bar as illustrated in picture below.

No alt text provided for this image

he reasons and solutions for the issue are described in this article.

Reason 1:

Primavera P6 schedules and displays the activities on Gantt chart very accurately, and up to the level of minute.

By default, the Data Date (blue line) is displayed at 00:00. The activities usually start at 08:00. That’s why there are gaps between the Data Date and the remaining bars.

Solution 1:

  • Go to menu Edit -> User Preferences. Select the option to show the time:
No alt text provided for this image

When running schedule (F9), set the time of Data Date to 08:00:

No alt text provided for this image

Finally, the gap has gone:

No alt text provided for this image

Solution 2:

  • Right click on Gantt Chart -> Select Bars
  • Change the value of Timescale of “Remaining Work” and “Critical Remaining Work” to “Current Bar”:
No alt text provided for this image

Select the “Actual Bar” and click the Shift Down button until its position is below the “Remaining Work” and “Critical Remaining Work” bar:

No alt text provided for this image

Finally, the gap has gone:

No alt text provided for this image

Explanation:

  • The “Current Bar” in Timescale represents the Start Date to Finish Date;
  • So, the “Remaining Work” and “Critical Remaining Work” bar are actually displayed from 29-Jan-20 to 02-Feb-20;
  • However, the “Actual” bar are displayed on top of “Remaining Work” and “Critical Remaining Work” bar. Therefore, the “Remaining Work” bar seems to start from the Data Date.

Reason 2:

The activity started out-of-sequence and Schedule Option is set to Retained Logic as illustrated in picture below.

No alt text provided for this image

Solution:

The gap could be removed by switching to Progress Override mode in Schedule Option. Then, the start date of remaining work of activity B will move to the Data Date.

No alt text provided for this image

Finally, the gap has gone:

No alt text provided for this image

Important Note:

The decision to change from Retained Logic to Progress Override mode has to be reviewed and approved by all relevant parties of the project.


Credits

Kudos

Ali Raza, BSc Civil Engineer, AssocRICS, PMP®

Contract Administrator, Planning Engineer, EOT, FIDIC Contracts, Variations, Claims, Delay Analyst, Dispute Adjudication Board (DAB)

4y

the reason is network logics and the path which is driving that specific activity with a gap. I dont use this pair of solution but to correct my network path

Zarak Nadeem (PMP)®

Program Scheduler- Ford Motor Company | Project Management Professional (PMP)®

4y

Stop copying others work and not giving them credit.

Radek Makar

Planning Director - ViViAD | Planning and Project Controls | Delay Analyst | Adjudication Party Representative | Accredited Mediator

4y
Usman Ghani

HSE SUPERVISOR /CIVIL ENGINEER/ OTHM LEVEL.6 /HSE DIPLOMA 3 YEARS /NEBOSH IGC/ISO/IOSH/FIRST AID

4y

Yes

Like
Reply

To view or add a comment, sign in

Insights from the community

Others also viewed

Explore topics