My Top 10 Tips for Using Power BI in Project Control

My Top 10 Tips for Using Power BI in Project Control

In the complex world of project control, Power BI has emerged as a game-changing tool for data analysis and visualization. Its potential to simplify complexity, deliver actionable insights, perform an interactive analysis and reduce time is unmatched—but only when used correctly. Here are my top 10 tips for leveraging Power BI effectively in project control to ensure your reports are both powerful and reliable.

1️⃣ Understand Your Data

Begin by building separate queries for each main data entry point, such as Baseline, Updates, Activity Codes, or Labor Units Distributions. Segmenting data at this stage reduces the risk of conflicts when combining datasets later.

2️⃣ Define a Star Schema

Simplify your data model with a Star Schema:

  • Use IDs like Activity IDs, Activity Code IDs, or Resource IDs as primary keys.
  • Avoid snowflake schemas that introduce unnecessary complexity.

In other industries, the data analyst often needs to perform multiple steps to establish the primary keys. We are so lucky to have these IDs in project control that work in our favour.

3️⃣ Optimize Data Types and Size

These steps might look minor but ignoring them will most likely produce errors and misleading results.

  • Assign appropriate data types (e.g., Decimals for costs fields, Percentages for the Activity % complete field).
  • Remove blank cells to prevent conflicts during calculations. Power BI will recognize blank cells as values and process them.
  • Eliminate redundancy—for instance, keep budgeted total cost in only one query to avoid duplications in calculations or processing errors.

4️⃣ Establish Clear Naming Conventions

Clarity is key. Use full, consistent names for tables, columns, and measures. When deadlines are tight and you are under pressure, clear naming prevents fatal mistakes and ensures that you don't select other fields by mistake. Instead of abbreviations, descriptive labels can save you.

5️⃣ Singularity is King

Stick to these principles for a more efficient model:

  • Use a single data source if possible.
  • Favor One-to-Many or Many-to-One relationships over Many-to-Many.
  • Set your cross-filter direction to Single rather than Both to maintain control over relationships.

6️⃣ Use More Measures

Rely on measures instead of calculated columns. Measures are optimized for Power BI’s engine which leads to better and even faster performance .

7️⃣ Test and Validate the Model

Test the water. Use a small set of your data (e.g., one small baseline and one update) to prototype and validate your model before scaling up. This approach is particularly helpful for beginners.

8️⃣ Build Your Relationships from Scratch

Disable auto-detect relationships and manually configure them. This extra effort prevents unintended joins and ensures your model reflects the true logic of your schedule's data.

9️⃣ Be Humble

Respect the tool, and it will respect you:

  • Work with data sources that you are familiar with to make troubleshooting easier in the future.
  • Avoid complex DAX expressions and pre-calculate them using measures where possible.
  • Focus on creating a reliable, error-free model rather than becoming obsessed with complex configurations.

🔟 Have a checklist

I am big fan of checklists. Don’t forget to have a checklist to review your model to cross-check the above points before finalizing! By following these principles, you’ll not only enhance your Power BI workflow but also deliver high-value insights that the project team relies on and desperately expects from planning engineers.

Regards,

Osama Saad, MBA, PMP, PSP, CCP, PMI-SP

Alaa Samir Hassan

Procurement engineer -Procurement Analyst-Project Procurement of materials and services -Data Analytics -SQL Data engineering -SAP S4/Hana Sourcing&Proc -MS Project -Autocad-Excel #Oil&Gas #Pharmaceutical

16h

Useful tips

Like
Reply

Can multiple projects be captured?

Like
Reply
Mohamed Ilyes Boucetta

Project Planning Engineer | Power BI & Primavera P6 | EPC Projects Control | 7+ Years in Oil & Gas | I help projects achieve completion on time & within budget

1w

Star Schema tip is key for better control of data very informative Osama

Like
Reply
Abdul Qadir

Deputy Manager Project Planning & Control| Primavera P6 | Microsoft Project | Power BI Developer | Excel Specialist |Google Certified Data Analyst

1w

Great insights, Osama! I’d like to add a few additional tips for optimizing Power BI models in project control: ✅ Organize your data model by placing dimension tables above fact tables to better understand filter context. ✅ Perform all transformations in Power BI rather than Excel for a more streamlined process. ✅ Use explicit measures instead of implicit ones to maintain control over calculations. ✅ Always consider the end user when designing reports and align visuals and KPIs strategically to ensure a smooth flow of information. ✅ Follow the "F" and "Z" patterns in data visualization to guide viewers effectively through the dashboard. These practices, combined with your tips, can truly elevate Power BI workflows in project control. Thanks for sharing!

Prashanth Kumar Bogi

Project Scheduler @Aramco | Primavera, Power BI Data Analyst | Passionate about Mega Projects | Driving 20% Cost Savings and 15% Faster Project delivery | Marathoner | Internet Data Center |

1w

Osama Saad, MBA, PMP, PSP, CCP, PMI-SP Informative post. Do you have prepared any detailed video from Extracting the data from Primavera to till the Dashboard (for any project). That will be more useful for PM.

To view or add a comment, sign in

Explore topics