Construction Claims Responses: The Consultant and Client Perspective

Construction Claims Responses: The Consultant and Client Perspective

Construction claims are an inevitable part of most projects. From the consultant’s and client’s perspective, the way claims are handled can significantly impact the project's financial and legal outcomes. A reliable claim review process and timely responses are critical to ensure a fair and quick resolution avoiding the need for time-consuming and costly escalation methods like arbitration or litigation. In this article, I explain the following consultant's roles in claims management.

1. Early Intervention

The consultant’s responsibility begins long before a claim is formally submitted.  Timely and accurate responses to the contractor notices and queries ensure the project remains on track and help prevent disputes. The consultant should also provide adequate responses to the contractor's delay notices.

  • Reviewing Schedule Updates: Regular and timely evaluation of the contractor’s schedule submissions is essential. This also includes verifying baseline schedules, actual progress and schedule changes.
  • Reviewing daily, weekly and monthly reports: Review and respond to any sections where the contractor mentioned inaccurate excusable delays. The response should be substantiated with documents.
  • Documenting Events: Maintaining a detailed record of project correspondence, schedules, and progress photos allows consultants to establish its own timeline of events.

Timely responses to notices and schedule submissions are critical. If the consultant delays responses, say by a year or more, the contractor may argue that the lack of objection implied consent which makes the delayed response invalid. This can weaken the client’s position, resulting in unfavourable outcomes in disputes.

2. Reviewing Claims

When a contractor submits a claim, consultants conduct the review which typically involves the following:

2.1. Reviewing Submitted Documents

The contractor’s claim often includes a package of supporting documentation such as:

  • Correspondences and notices.
  • Updated schedules
  • Causation and delay analysis
  • Narrative Report

The consultant’s first task is to confirm whether these documents align with the contractual requirements. For example, was a notice submitted within the stipulated timeframe after the event occurred?

2.2. Delay Analysis

Every delay analysis method has its own advantages, disadvantages, strengths, weaknesses, uses and limitations. First, ensure that the selected method is appropriate. Otherwise, if the method is not suitable for the project circumstances, the whole claim can be thrown out of the window. For example, in a large complex project, you'd better have a very good reason for why you would choose weak methods such as Impacted-As-Planned in your analysis.

2.3. Counter-arguments

The consultant often reviews the contractor's claim submission as it is. In other words, the consultant is in the defence mode. However, consultants are recommended to prepare counter-arguments. For example, the consultant can prepare its own delay analysis, identify contractor's risk events and even create fragnets that evaluate the contractor's delays. In these cases, it is not uncommon to have a claim response that is bigger than the claim itself.

2.4. Drafting the Outcome

The outcome of the review typically falls into one of three categories:

  1. Approved: The contractor’s claim is valid and accepted, either fully or partially.
  2. Rejected: The claim lacks merit due to non-compliance of the contract, lack of evidence, misrepresentation of facts, poor delay analysis or unfair data manipulation (very common by the way).
  3. Further Clarification Required: The consultant requests additional information from the contractor (e.g. missing some P6 XER files).

3- Timely Responses

If a consultant fails to respond to a schedule update or notice promptly, this could weaken the client's case. The contractor may argue that the delay implies acceptance of their claims or position. Moreover, regular schedule updates and progress reports are required for a good reason which is to help project parties understand the progress status and take an appropriate action based on what they see in the report. Therefore, if the consultant took one year to respond to a schedule update, the response  doesn't really help anyone at this stage. As a result, most contracts require notices and claims to be submitted within strict timeframes. Contractors who fail to comply with these requirements risk their claims being rejected entirely. Late submissions - whether by the consultant or the contractor often result in unfavourable outcomes to the responsible party.

Contractors sometimes believe that submitting claims at the end of the project without notices will be just as effective as timely submissions. This approach is Naïve: The lack of timely notices as required by the contract can invalidate claims entirely. In practice, notices are meant to inform all project parties of potentials delays and encourage them to work together and mitigate the impact. Waiting until the end of the project ignores the importance of contemporaneous records and notifications which will make the claim open to significant challenge by the opposition.

Regards,

Osama Saad, MBA, PMP, PSP, CCP, PMI-SP

C P Gamage

Planning Engineer | Expert in Project Scheduling | PMP®

5d

Very helpful.. Thank you for sharing Eng. Osama

To view or add a comment, sign in

More articles by Osama Saad, MBA, PMP, PSP, CCP, PMI-SP

  • 🚧Humanity Over Toxicity In Construction🚧

    🚧Humanity Over Toxicity In Construction🚧

    The construction industry often normalizes toxic behaviours and rude treatment justified by statements like: 1️⃣ "This…

    3 Comments
  • How to Start a Career in Planning: A Practical Guide

    How to Start a Career in Planning: A Practical Guide

    Starting a career in planning can feel overwhelming, especially if you're transitioning from another role or just…

    8 Comments
  • Are Project Control Certifications Really Necessary?

    Are Project Control Certifications Really Necessary?

    When it comes to certifications in project management and project controls, one common question arises: "Are…

    4 Comments
  • Top 11 Power BI Formatting Tips for Project Control

    Top 11 Power BI Formatting Tips for Project Control

    When it comes to project control, presenting your data with clarity and consistency is essential. Power BI is a…

    3 Comments
  • My Top 10 Tips for Using Power BI in Project Control

    My Top 10 Tips for Using Power BI in Project Control

    In the complex world of project control, Power BI has emerged as a game-changing tool for data analysis and…

    6 Comments
  • Common Pitfalls in Submitting EOT Claims

    Common Pitfalls in Submitting EOT Claims

    Delay claims are an inevitable part of the construction industry. While claims can protect a contractor’s entitlement…

    11 Comments
  • 20 ways to show mitigation for excusable delay

    20 ways to show mitigation for excusable delay

    When planning engineers conduct delay analysis and prepare an extension of time claims, they often face confusion about…

    18 Comments
  • Excusable delay mitigation in EOT claims

    Excusable delay mitigation in EOT claims

    Most modern contracts require the contractor to "mitigate" the delays even though such delays are beyond its reasonable…

    11 Comments
  • Longest Path vs Critical Path

    Longest Path vs Critical Path

    Many planning engineers experience confusion regarding the difference between the longest path and the critical path…

    14 Comments
  • Managing Schedule Delays

    Managing Schedule Delays

    How should we manage the schedule delays? Should we make regular schedule changes to ensure that the schedule updates…

    19 Comments

Explore topics