I'm excited to share with you my achievement in my land surveying career. Over the past few weeks, I was busy setting up this Overhead Traveling Crane (OHTC) lane which is 21.080 meters apart. The following requirements were adhered to when setting up the OHTC: 1: Alignment along one rail 2: Height difference along one rail 3: Parallelism of two lanes 4: Height difference between two lanes parallel to each other. The task was quite challenging, but it was executed with maximum care, and eventually, the required accuracies were attained. As a result, it had to be tested before the operation started. The tests included: 1: Functional test 2: Load test 3: Static load test 4: Dynamic test It was a remarkable experience indeed. #surveylife #surveyors #sokkia