Longest Path vs Critical Path

Longest Path vs Critical Path

Many planning engineers experience confusion regarding the difference between the longest path and the critical path. This article explains the definition, focus and use case for both. A spoiler alert: the longest and critical paths are not the same. In fact, the longest and critical paths are different to the extent that P6 offers separate filters, columns, grouping and presentation for both. The difference is more prominent in the schedule updates during the project execution as demonstrated in the below image. When a schedule update is completed, critical paths can be generated whereas the corresponding scope of each path is completed beyond the contract completion date. This dynamic is better analyzed through a multiple float paths framework. On the other hand, the “Longest Path” is the longest sequence of activities among other competing critical paths. This path is what drives the forecasted completion date and is driven by the dominant cause of the overall project delays. The below image is for demonstration purposes only as you might have more critical paths in your project.


Longest Path

Definition: It is the longest sequence of activities that drives the forecasted schedule completion date.

Focus: It focuses on the “longest” chain of activities and the dominant driver of the forecasted completion date.

Use Case: The longest path analysis is more prominent in the schedule updates. This analysis can examine how the forecasted completion date is derived because it can effectively determine the longest sequence of activities among other competing critical paths.

Critical Path

Definition: It consists of activities that have a total float amount of less than or equal to zero. Although the total float amount that determines the criticality threshold can be customized inside Primavera P6 under the scheduling options (refer to the below snapshot), zero is the industry standard.


Focus: It focuses on the most critical tasks that directly impact the contract’s completion date.

Use Case: The critical path analysis is used in both the baseline schedule and the schedule updates. However, in the schedule updates, the critical path analysis will produce distinct results over using the longest path analysis alone. Analyzing the multiple float paths is an effective method for performing critical path analysis during project execution.

Identifying the Longest and Critical Paths

There are some ways to identify and recognize both the longest path activities and the critical path activities in P6. However, I will only cover the most common features that I personally use.

1- Filter

You can filter the longest path and critical activities as highlighted in the below image.


2- Activity Columns

You can add “Critical” and “Longest Path” columns to your activities layout as below:

3- Grouping

You can group your activities by whether the activities are “Critical” or  “Longest Path” as per the image below.


Finally, I would like to add two final points you need to consider while analyzing the critical path and longest path activities.

  • In the baseline, the critical and longest paths are the same.
  • In the schedule update, a critical path is not necessarily the longest.
  • The longest path is always a critical path except when the forecasted completion date is earlier than the contract completion date. In this case, the longest path will show a positive float and therefore, it is not critical. However, this is rarely the case. In my experience, Contractors do not often submit a schedule update that shows a completion date that is earlier than the contract completion date.

Conclusion

To sum up, the critical path and longest path analyses can shadow each other but are not the same. Performing any of both analyses will depend on your objective and which schedule version you are using.

Regards,

Osama Saad, MBA, PMP, PSP, CCP, PMI-SP

Fady Joseph

Civil Engineer I Site Engineer

5mo

Very informative, Thank you for sharing.

Like
Reply
Mohammadreza Shahrad

BSc., PMP, EIT, Project Planner/Scheduler

5mo

Thank you for sharing

Siddhartha Kadavupuzha, PMP®

Strategy & Business Consulting | Risk Management | Project Management | Capital Projects

5mo

This is indeed a very clear and crisp explanation and an eye opener. Many firms spend a lot of effort monitoring the critical path just based on the float criteria, whereas the longest path is hardly focussed upon. This blog is quite spot on pointing out the major difference. I would be looking forward to hearing from you about which is the preferred method based on the phase a project is operating in and how that impacts the overall monitoring and forecast assurance.

Mariam Elsheikh

Planning Engineer @ Altorath International Engineering Consultants L.L.C (AIC) | Project Scheduling, Delay Analysis

5mo

Very informative

Ekrem Sülün,MBA,PMP,PMI-SP

Planning & Cost Department Manager at Exacons Company | MBA, PMP, PMI-SP, Oracle-Primavera P6 / Project Mng / Earned Value Mng / Risk Mng / Planning & Cost Control & Reporting Expert, PMI-TR Volunteer

5mo

A nice and educational article. I like using the definition "The longest path is the critical path, but not every critical path is the longest path". In the construction industry, I use the longest path more because it shows the deviation & estimated completion date for schedule updates, more objective, looking big picture, while the critical path can change depending specific values (deadline, constraint, etc.), can be multiple & more subjective, focusing to prioritize tasks & using resource allocation effectively, indicates specific critical activities which important to me.

Like
Reply

To view or add a comment, sign in

Insights from the community

Others also viewed

Explore topics