HURRICANE PREPAREDNESS: BEST PRACTICES FOR ADVERSE WEATHER (white paper)
INTRODUCTION
From June to November, any job site along the Gulf Coast could quickly turn hazardous due to the arrival of storms, tropical storms, and hurricanes. Whether basic thunderstorms or severe hurricanes, every project team hopes to avoid weather conditions that put workers at risk and potentially cause considerable damage. To minimize damage and ensure workers are safe, it is critical construction companies follow best practices when preparing for adverse weather conditions and implement detailed preparedness plans.
PREPARING FOR ADVERSE WEATHER CONDITIONS
Proactive preparation ensures workers stay safe and projects stay on schedule, and project teams should begin adverse weather preparations long before a storm or hurricane strikes.
EMPLOYEE PREPAREDNESS
The basis of any effective response is employees’ ability to anticipate the needs of Owners, job sites, and personnel during a potential weather event. Encourage all employees to make their own personal preparedness plan to protect their family and personal property. Offer training and other informational resources to educate employees on safety practices for storms and hurricanes. This proactive approach ensures employees will be ready, willing, and able to assist Owners and job sites with storm preparations when needed.
BASIC WEATHER MONITORING
Basic weather monitoring is a best practice on every job site and should be part of the project team’s daily responsibilities. Every project team should check incoming weather before work begins and continue to monitor the forecast throughout the day. Teams who consistently monitor the weather are more able to adjust their work when adverse conditions arise and keep workers safe.
SCHEDULING
When beginning any construction project, first approach the Owner and highlight areas where the proposed schedule or scope overlaps with typical periods of adverse weather, such as hurricane season. If proposed construction activities overlap with hurricane season, communicate this potential challenge to all stakeholders and ensure the job site guidelines address weather monitoring practices.
ALLOCATING FUNDS
Before starting construction, determine what a job site will need in the event of adverse weather. For example, high winds from an incoming hurricane may require the project team to cover windows and dismantle and re-erect scaffolding. Bring these potential needs to the Owner and suggest allocating money for these activities and any required materials before they are needed. The Owner may choose not to include funds for these activities, but proactively addressing potential issues increases the likelihood a project team will be prepared.
PROCURING MATERIAL EARLY
Weather is unreliable and can change dramatically without warning. Rather than waiting until a thunderstorm, tropical storm, or hurricane is nearby and materials are more in demand and expensive, procure any materials required to secure a job site early. Procuring materials like plywood, sandbags, and plastic sheeting as far in advance of adverse weather as possible also ensures the project team can tailor the materials to the job site
MAINTENANCE CHECKS AND TESTS
Before weather events occur, evaluate the job site to determine whether any back-up equipment or emergency systems need repairs. Identify what the facility needs to withstand high winds and potential flooding conditions and take precautionary measures to avoid damage to the job site. For example, the project team should check the following facilities before potential flooding conditions:
HURRICANE PREPAREDNESS
Project sites located near the Gulf Coast are under constant threat from hurricane-like conditions. Good construction companies will issue a hurricane procedure manual and hurricane preparedness plan every year with the latest information on how to combat hazardous weather conditions. Once issued, implement the plan on every job site and discuss it weekly with the Owner to address risks and put reactive actions in place.
Recommended by LinkedIn
Additionally, the management team should review the plan at the beginning, middle, and end of the hurricane season, and they should adjust the plan according to the status of construction. Read on for an explanation of some basic topics covered in a good hurricane preparedness plan.
EMERGENCY CONTACT LIST
Provide employees with a detailed project directory containing emergency contact information for all essential members of the project team. The project directory should include the company name, the company representative’s name, an office number, and a cellphone number. It should also include contact information for:
SAMPLE HURRICANE PREPAREDNESS PLAN
Below is an excerpt from a sample hurricane preparedness plan addressing steps to take in the event a hurricane becomes a threat to a job site. Use this excerpt as an example or reference when creating a site-specific hurricane preparedness plan.
1. Update the project directory with emergency contact information. Complete this process at the beginning of hurricane season and again when tropical storm or hurricane paths project an entry into the job site’s area.
a. The labor coordinator should gather phone numbers and shelter information for all workers.
b. Encourage trade contractors to gather phone numbers for their workers as well.
2. Monitor hurricane tracking charts for the path of the storm.
3. Make sure all project personnel know the job site evacuation route (obtain maps, if possible).
4. Ensure each job site is equipped with a battery-powered AM radio and a radio that strictly monitors weather information.
5. The field coordinator should determine whether the Owner requires any special preparation measures. Review requirements with the communications coordinator.
6. The field coordinator should determine what areas of the project may be prone to flooding so the project team can plan extra precautions.
7. The field coordinator should identify local vendors in case extra material is needed (plywood, plastic sheeting, etc.). In less populated areas, more than one vendor may be necessary.
8. The plan coordinator should review the builder’s risk policy for the project.
ABOUT VAUGHN CONSTRUCTION
Vaughn Construction is a Texas-based construction company that specializes in new construction, renovations and additions to civic, healthcare, education and research facilities. The privately-held company has offices in Austin, Bryan/College Station, Dallas/Fort Worth, El Paso, Houston, Lubbock, San Antonio, and the Texas Medical Center (Houston). For additional information, visit www.vaughnconstruction.com
Vaughn responds to significant flooding in Houston during Hurricane Harvey
President of the Stormwater Training Center
2yGreat advice and information. Hurricane preparation strategies are often overlooked and become more reactive than proactive. Great job!
Construction Growth Strategist | Enjoy the journey with 2X Cash, 3X Profit, 10X Valuation
2yThank you for this good reminder.