Project/Schedule Recovery: Beyond Crashing and Fast-tracking

Project/Schedule Recovery: Beyond Crashing and Fast-tracking

Hej to all Project Team and Planners,

How do you recover a derailing project schedule? The usual response, especially by anyone who has passed through the PMP, is Crashing and Fast-tracking.

Right, but schedule recovery is not only about crashing and fast-tracking; there are other methods you can deploy to recover your schedule and project.

Before I go into them, one thing we have been taught is that fast-tracking does not increase the project cost, just only risk but this is not always true. There are actually direct costs, but most importantly indirect costs like the cost of managing an additional unplanned increase in cost as well as the cost of risks. I explained the cost implications of fast-tracking a project on this article: Cost Implication of Fast tracking a Project.

Another critical cost impact of fast-tracking on your project is that it will distort your planned cash flow!


How do you recover your project outside crashing and fast-tracking?

  1. Project Calendar- Increased Hours Per Day: You can recover your project by modifying the Work Calendar like extending Hours worked per day from 8 to 10/12 hours.
  2. Project Calendar - Increased Work Week Days: if you are currently working like 5 days per week, you can adjust your work week to 6 or 7 days per week.
  3. Project Calendar - Increased Work Shift: you can introduce additional shifts per day.
  4. Scope Reduction - In an extreme case, you may decide to cut off some scopes. Clients may withdraw scopes from contractors or as a contractor, you may decide to outsource some scopes.

Note that you are not limited to using only one type of schedule recovery technique. You can combine many different types to get the optimal savings.

Also, certain considerations need to be made like

  • local regulations, cultural, and other factors can limit your use of certain recovery techniques like some places will never accept working on weekends.
  • Working extended hours/days for a long time may lead to burn-out among your resources
  • Putting additional resources may result in Brooks' Law - diminishing or negative returns instead of schedule recovery.

One thing I always advise is for you to analyze the risks related to any choice or choices for recovery method/s chosen for your project.


Another thing that will be awesome for your project is to have a project/schedule recovery plan. See this article on Creating a Project Recovery Action Plan.

What do you think?

Are there any other project recovery techniques?

Barry Fullarton

Contract Specialist/ NEC and FIDIC / Extension of Time Expert/ Adjudicator

4d

What would be good to know is how many projects are experiencing these issues

Like
Reply
ANAS MOHAMMED

Planning Engineer Experienced In High-rise Buildings | Cost Control | Cost Estimation

1w

I found the topic of your article very engaging. I was particularly interested in exploring alternative project acceleration methods beyond the typical crashing techniques. While the article presented four valuable techniques, it appears that all four methods are categorized as crashing techniques. I think there are ways beyond crashing and fast tracking, such as:-  1- improve the efficiency of the team by implementing different motivation techniques.  2- increase the level of details of the schedule to tackle the idle time in/between activities.  3- find the most impactful causes of the delays by following 20/80 rule, from my experience there is usually a clear pattern for the causes of delays in each project, 80% of delays are having the same 20% of causes. 4- ensure the resources are fully employed.

Bruce Cohoon

Senior Scheduling Manager

1w

Ok, I'm going to be my usual self and anti-advocate on this post, so forgive my digression into being a superintendent. What this article talks about is how to use features within a software program to create dates that everybody loves/wants. This does nothing to lead the Project team toward a successful recovery of the work. Instead, what is needed is the Scheduling Manager must call for an immediate Pull Meeting to determine 1) Cause and Effect, 2) Currect Degree of Impact, 3) Determine Plausible Courses of Actions That Are Most Likely To Result in Recovery (new risk review) and 4) Submit the Best Courses of Action to Management for Action and Direction. Now you'll know what your team is not only capable of doing, but what they're willing to commit to doing.

Zoltan Palffy

Project Scheduler - GPSF - M.C. Dean

1w

the 4 items that you mentioned really do fall under the crashing the schedule because by modifying the calendar you are in essence increasing the working times thus reducing the duration the same TECHNIQUE as crashing. Except for item #4 scope reduction

To view or add a comment, sign in

Insights from the community

Others also viewed

Explore topics