Bengaluru Metro Yellow Line: Titagarh to dispatch first train on Jan 6, says Tejasvi Surya

The 19-km Yellow Line (RV Road-Bommasandra) was initially scheduled for completion by the end of 2021 but faced delays due to multiple factors.

January 02, 2025 / 09:19 IST
Story continues below Advertisement

The 19-km-long Yellow Line was supposed to be operational in 2021

After missing multiple deadlines, Bengaluru Metro's long-awaited Yellow Line (RV Road-Bommasandra), which connects Electronics City—home to companies like Infosys and Biocon—is finally on track.

"We now have the first train ready to be dispatched to Bengaluru on January 6. Titagarh Rail Systems has committed to delivering the second train by the end of January or the first week of February and the third in April. Thereafter, they will deliver one train per month and scale up to two trains per month by September," Bengaluru South MP Tejasvi Surya said on January 2.

Story continues below Advertisement

"I have requested the Union Minister for Housing and Urban Affairs to visit the manufacturing plant on January 6, flag off the trains to Bengaluru, and inspect the plant to help expedite the process. I will also be present in Kolkata for the event," Surya added.

Also read: Prototype train for Bengaluru Metro's Purple Line shipped from China's CRRC