Exciting Progress at Ensus with Major Dryer Replacement!
In late September, Ensus UK Ltd marked a significant milestone in the Dryer Replacement Project with a successful shutdown involving a complex removal and installation of the new "A" Dryer. This essential upgrade will improve the plant’s efficiency in producing #DDGS (Distillers’ Dried Grains) which is a high-grade #AnimalFeed.
Project Highlights:
✔ Precision Planning: The project required a 1,350-ton Schaften crane to manage the complex logistics. In the first week, the original dryer was disconnected and removed, making way for the new triple-pass rotary drum dryer built onsite.
✔ Safety First: To minimize disruption, critical lifts were scheduled over weekends, while strict safety protocols ensured a safe and seamless execution.
André Tonneaux from CropEnergies AG commended the team’s meticulous handling, stating: "Indeed, a very good performance for such a heavy load (300t) in such a compact area. Well done to the Ensus team, led by Jason Wildmore!"
Since the plant went operational 14 years ago, dryers "A" and "B" have been pivotal in the overall success of the plant.
Here’s to more successful upgrades and to the continued commitment of our teams and partners to safety and excellence in project delivery!